Geotech Drilling Services has completed numerous notable projects, each with varying objectives and magnitude but some that we consider most prominent are included below.

Resiance Project
Calgary, BC

11811 Lake Fraser Drive SE
Completed 17,600 feet of geothermal drilling and installation.

Cielo Condominium Project
Vancouver BC

1201 West Hastings Street,
February and March 2005
Completed 28,000 feet of geothermal drilling and installation.

Watson Lake Airport
June 2004
Hollow stem augering, split spoon sampling and monitoring well installations in sands and gravels. 3 day drilling program

South Peace Realignment
Spring/Summer of 2003
This project was the completed with our B-53 track rig and Simco Explorer
Approximately 10,000ft of Horizontal Drain pipe was installed in bedrock at + 10 degrees off horizontal. Approximately 1500ft of HQ3 soil coring in clay with installation of Slope Inclinometers in each hole Approximately 800 ft of Pneumatic Piezometers drilled and installed by Air rotary methods

Sun Rivers Community
Kamloops, BC

Nov 2002 to present
Drilled and installed to date over 50,000 feet of Geothermal loops.
Terasen Multi Services Utility Corporation now owns project.
Will continue for next 7-10 years.

Nida lake Lodge
Whistler, BC

Earth Source
Completed 28,000 feet of geothermal drilling and installation.

Pointe of View
Kelowna, BC

May 2004 to September
Drilled and installed 33,000 feet of geothermal loops.

Glacier Creek Contracting
Pemberton, BC

September 2003 to May 2004
Completed 47,000 feet of geothermal drilling and installation.

Sept – Nov 2002 Amec Earth & Environmental
Quesnel Slide Investigation

Multiple HQ3 BH’s up to 505 ft. with soil & bedrock
Sampling – piezo & S.I. installs
June -Sept 2003

TRANSLINK and Golder Associates
Richmond Airport Vancouver Connector - RAV Line

We utilized our B-80 and B-53 Track rig for this contract
The work consisted of HQ3 soil coring to depths of 150ft.
In addition HQ3 coring of bedrock when encountered
Approximately 50 holes were drilled over the course of the summer.


Sun Rivers Community in Kamloops

Nov 2002 to present
Drilled and installed to date over 50,000 feet of Geothermal loops.
Project is now owned by Terasen Multi Services Utility corporation.
Will continue for next 7-10 years.

 